ENGINEERING SELECTION AND AWARD
Completed February 1, 2010
Evaluate Existing System, Model, & Prepare Cost Estimates
Completed
WATER SYSTEM CONTRACT
Prepare Construction Drawings & Bid Documents - Completed May 31
State Review Drawings & Bid Documents - Completed Jun 17
Make Revisions to Drawings & Documents - Completed Jun 30
State Final Review of Drawings & Documents - Completed Jul 15
Advertise for Bid - Completed
Construct Water System Improvements - in process
WELL DRILLING CONTRACT
Perform Well Geologic Study - Completed Apr 23, 2010
Prepare Preliminary Evaluation Report (PER) - Completed Jun 2, 2010
State Review & Approval of PER - Completed Jul 21, 2010
Prepare Well Drilling Plans & Specs & Easements - begin Jul 21, completed
State Review & Approval of Well Plans & Specs - completed
Advertise for Bid - completed
Construct Well Drilling - in process
Test Pumping Well - in process
Prepare Source Protection Plan (DWSP) - in process
State Review & Approval of DWSP - in process
WELL PUMPING FACILITY CONTRACT
Well Pump Facility Design & Bid Documents - completed
State Review & Approval of Plans & Specs - completed
Advertise for Bid - completed
Protest Period - completed
Construct Well Pumping Facility - begin April 2011
FINALIZE ALL PROJECTS WITH STATE
Fall 2011